File #: 17-099    Version: 1 Name: AUTHORIZATION TO ENTER INTO A GRANT AGREEMENT WITH THE ARIZONA DEPARTMENT OF TRANSPORTATION FOR NORTH APRON REHABILITATION PHASE ONE PROJECT
Type: Consent Resolutions Status: Passed
File created: 3/7/2017 In control: City Council
On agenda: 3/28/2017 Final action: 3/28/2017
Title: RESOLUTION NO. R17-22 A RESOLUTION OF THE COUNCIL OF THE CITY OF GLENDALE, MARICOPA COUNTY, ARIZONA, AUTHORIZING THE ENTERING INTO AND ACCEPTANCE OF A GRANT FROM THE ARIZONA DEPARTMENT OF TRANSPORTATION, MULTIMODAL PLANNING DIVISION, FOR THE REHABILITATE NORTH APRON, PHASE ONE PROJECT AT THE GLENDALE MUNICIPAL AIRPORT. Staff Contact: Jack Friedline, Director, Public Works
Attachments: 1. Resolution No. R17-22, 2. Airport Development Reimbursable Grant Agreement

Title

RESOLUTION NO. R17-22

 

A RESOLUTION OF THE COUNCIL OF THE CITY OF GLENDALE, MARICOPA COUNTY, ARIZONA, AUTHORIZING THE ENTERING INTO AND ACCEPTANCE OF A GRANT FROM THE ARIZONA DEPARTMENT OF TRANSPORTATION, MULTIMODAL PLANNING DIVISION, FOR THE REHABILITATE NORTH APRON, PHASE ONE PROJECT AT THE GLENDALE MUNICIPAL AIRPORT.

Staff Contact:  Jack Friedline, Director, Public Works

end

Purpose and Recommended Action

Recommendation

 

This is a request for City Council to waive reading beyond the title and adopt a resolution authorizing the City Manager to enter into a Grant Agreement with the Arizona Department of Transportation (ADOT), in the amount of $42,465, for reimbursement of the North Apron Rehabilitation Phase One project at the Glendale Municipal Airport.

Background

 

The North Apron area comprises parking and service areas for small aircraft. Recent pavement management reports indicate the area is in need of rehabilitation. Phase One includes miscellaneous environmental study, project design, and pavement reconstruction in an amount available through federal and state funding. 

 

In April of 2016, the City entered into a Professional Services Agreement with Dibble & Associates Consulting Engineers, Inc. for design of the North Apron Rehabilitation. This firm also assisted in the development of a bid package for Phase One reconstruction. Five bids were received and city Council approved a Construction Agreement with Combs Construction on October 25, 2016. Phase One rehabilitation is now complete with a construction cost of $583,337.37.

 

Future phases to complete the rehabilitation of the north apron, including additional areas of reconstruction (estimated at $4,707,580) and areas of mill and overlay (estimated at $1,092,500), will be scheduled, bid, and brought to City Council as federal funding becomes available, likely in summer of 2017.

 

Analysis

 

The Federal Aviation Administration (FAA) and Arizona Department of Transportation (ADOT) has emphasized the priority for federal and state grant money to be allocated for airport pavement projects to protect the long-term investments that have been made to the nationwide and statewide airport system. To receive grants, airports must complete the design and request reimbursement when the construction project is bid or complete, depending on the agency.

 

This Grant Agreement with ADOT will reimburse the city $42,465 expended as part of the North Apron Rehabilitation Phase One project.

Previous Related Council Action

 

On October 25, 2016, City Council authorized entering into Amendment No. 1 to the Professional Services Agreement with Dibble & Associates Consulting Engineers, Inc., Contract No. C-10792, for construction administration services and testing for the North Apron Rehabilitation Phase One project, increasing the compensation by $39,539 to a not to exceed amount of $403,850.

 

On October 25, 2016, City Council authorized entering into a Construction Agreement with Combs Construction, Contract C-11268, for the construction of the North Apron Rehabilitation Phase One project, in an amount not to exceed $543,798.37.

 

On August 9, 2016, City Council authorized entering into Federal Aviation Administration Grant 3-04-0064-025-2016 in the amount of $865,070, to reimburse the city for funds expended as part of the North Apron Rehabilitation Phase One project.

 

On April 12, 2016, City Council authorized entering into a Professional Services Agreement with Dibble & Associates Consulting Engineers, Inc., Contract No C-10792, for the design services of the North Apron Rehabilitation project, in the amount not to exceed $292,205.

 

Community Benefit/Public Involvement

 

The Airport plays an important role in meeting the demand for aviation services in the West Valley and serves as a general aviation reliever airport for Phoenix Sky Harbor International Airport.

 

The Airport Administrator provides updates on this and other projects to the Aviation Advisory Commission during its monthly meetings. The Aviation Advisory Commission approved the following motion at the February 15, 2017 meeting: This is a recommendation for the City Council to adopt a resolution authorizing the City Manager to enter into a grant agreement E7F3G01C with the Arizona Department of Transportation (ADOT) in the amount of $42,465 for the North Apron Rehabilitation - Phase One at the Glendale Municipal Airport.

Budget and Financial Impacts

 

There are no costs to the city as part of this action. This Grant Agreement will reimburse the city for funds expended under previous City Council direction.