File #: 16-404    Version: 1 Name: AGREEMENT WITH VIASUN CORPORATION FOR THE PAVEMENT MANAGEMENT PROGRAM SLURRY SEAL PROJECT
Type: Consent Status: Passed
File created: 8/19/2016 In control: City Council
On agenda: 9/13/2016 Final action: 9/13/2016
Title: AUTHORIZATION TO ENTER INTO A CONSTRUCTION AGREEMENT WITH VIASUN CORPORATION FOR THE PAVEMENT MANAGEMENT PROGRAM SLURRY SEAL PROJECT Staff Contact: Jack Friedline, Director, Public Works
Attachments: 1. Construction Agreement, 2. Bid Tabulation 151630
Title
AUTHORIZATION TO ENTER INTO A CONSTRUCTION AGREEMENT WITH VIASUN CORPORATION FOR THE PAVEMENT MANAGEMENT PROGRAM SLURRY SEAL PROJECT
Staff Contact: Jack Friedline, Director, Public Works
end
Purpose and Recommended Action
Recommendation

This is a request for City Council to authorize the City Manager to enter into a Construction Agreement with Viasun Corporation in an amount not to exceed $1,958,963.10 for the Pavement Management Program Slurry Seal project.
body
Background

The city has over 748 miles of paved arterial, collector and residential roadways, which represents an investment of over $1 billion in the street network based on replacement costs in today's economy. With the exception of minor street and concrete repairs (potholes, small paving projects, curb, and sidewalk repairs) the city currently contracts for all other preventative maintenance and reconstructive roadway projects.

The Slurry Seal Project for the Pavement Management Program provides for approximately 30 miles of slurry seal surface preservation on various arterial, collector and residential streets throughout the city. Specifically this project includes: slurry surface treatment of existing roadway sections, and thermoplastic restriping or repainting of pavement markings.
Analysis

The Engineering division published a Notice to Contractors requesting bids for the Pavement Management Program - Slurry Seal (project number 151630) on May 19, and 26, 2016. Six contractors obtained the bid documents. On July 7, 2016, two bids were received, with Viasun Corporation submitting the lowest responsive and responsible bid in the amount of $1,958,963.10. Staff anticipates issuing a Notice to Proceed late September, with construction beginning October 2016.
Previous Related Council Action

On April 5, 2016, staff presented the five year Pavement Management Program to Council.

On June 9, 2015, Council authorized a construction agreement with VSS International, Inc., in the amount no...